What Is a Progress Payment?
A staged partial payment of a building contract, made when the build reaches a defined milestone. The payment structure used in almost all Australian residential building contracts.
Definition
A progress payment is a partial payment of the total contract price, paid when the build reaches a defined physical milestone. Most Australian residential building contracts use a 5-stage or 6-stage progress payment schedule: deposit, base, frame, lock-up, fixing, and practical completion.
Progress payment schedule example: a $600,000 new home
This worked example applies the Victorian statutory stage split for a contract that covers every stage (Domestic Building Contracts Act 1995 (Vic), section 40) to an illustrative $600,000 contract. Other states leave more of the split to the contract, so check the schedule in your own contract before relying on these figures. On BuildFair, a new home runs as a 5% deposit (10% in NSW), ten stages of 8.5%, and the final 10% at completion, each stage funded before the work starts.
| Stage | Share | Payment | Paid to date | Claimable when |
|---|---|---|---|---|
| Deposit | 5% | $30,000 | $30,000 | Contract signed and required insurance in place |
| Base | 10% | $60,000 | $90,000 | Footings and slab (or base floor) complete |
| Frame | 15% | $90,000 | $180,000 | Wall and roof frames up and approved |
| Lock-up | 35% | $210,000 | $390,000 | External walls, roof, windows and external doors installed |
| Fixing | 25% | $150,000 | $540,000 | Internal linings, cabinetry, doors and fit-off items fixed |
| Practical completion | 10% | $60,000 | $600,000 | Work finished, with the occupancy permit or certificate of final inspection issued |
Checks before paying each stage
- The claim names the stage and matches the percentage in your contract schedule.
- Evidence shows the stage is actually complete, such as photos or an inspection or certifier sign-off where one applies.
- Any approved variations are listed separately, so the contract sum still reconciles.
- You pay or raise a written dispute within the period your contract sets.
Deposits have their own limits. In Victoria the deposit is capped at 5% for contracts of $20,000 or more, and in New South Wales at 10%. To compare a schedule before you sign, see the standard progress payment schedule. For how a stage claim is assembled, approved and paid out to trades in one run, see how progress payment software works, or book a BuildFair demo.
Why it matters
Progress payments are the financial backbone of every Australian residential build. They determine how much money the owner pays at each stage, how the builder funds the build between stages, and where the risk sits when something goes wrong. Most owners encounter the term for the first time when reviewing a building contract and don't fully understand the implications until something goes wrong mid-build.
How it works in practice
When the builder reaches a stage in the build, they issue a progress claim to the owner (or to the bank if the build is funded by a construction loan). The progress claim is an invoice for the next stage payment, accompanied by some form of evidence that the stage has been reached. The owner or bank reviews the claim and either pays it or disputes it within a defined window (typically 14 days under most contracts).
If paid, the funds go into the builder's general operating account. The funds are not held in trust, are not ringfenced for the trades who did the work on that stage, and can be used by the builder for any project or business purpose.
The percentages vary by contract and by state. Victoria sets the split for a contract covering every stage at deposit 5%, base 10%, frame 15%, lock-up 35%, fixing 25% and practical completion 10%. The worked example on this page applies that split to a $600,000 contract.
Common misconceptions
Progress payments are held in trust
They aren't, in standard Australian residential contracts. Owner funds become the builder's funds the moment they're paid.
A progress claim is the same as an invoice
Not under the Security of Payment Act. A progress claim with the right wording becomes a payment claim under the Act, which triggers specific legal protections for subcontractors and suppliers. A standard invoice without that wording does not.
The percentages are fixed
Some are capped by state legislation (Victoria caps deposits at 5% for new homes, for example), but most are negotiable at contract signing within industry-standard ranges.
For the full structure, see the How progress payments work in Australian residential construction pillar.
Related terms
How BuildFair changes this
Managing a residential build? See how BuildFair manages construction payments, so builders and trades work from the same record of their claims and payments, and owners follow the build through photos and progress updates.
For owners
Your money sits in your name and only moves against claims on your job
How progress payments work
The staged payment ladder every residential build runs on